Confirmation of Changes

Confirmation of Changes

What is a "confirmation of changes document"? 

A confirmation of changes is just that, a confirmation that each change was in fact completed in the die design. 
Before T-SIM service can proceed to the press setup package, we need to be confident that settings we are providing will in fact setup and run without issues. The only way for us to do this is to either simulate the finalized die design one more time or have the die designer provide us a document which shows all of the issues have been corrected in the design. 

Some stampers may require a full recheck simulation. If they do allow a confirmation of changes, then we will specify that when we deliver the R2 or recheck report. 

What format is required for the "confirmation of changes document"? 
T-SIM is flexible regarding the specific format (Word, PDF, Powerpoint, etc.)

We only expect the following 3 things in the document (for EACH ISSUE)
1- The Specific Issue # from the T-SIM CAR (What issue is being addressed)
      - An image of the CAR page is also acceptable
2- The Specific dimensions or distance that was changed 
      - An image showing the change with measurements is also acceptable
3- A brief explanation of how the change was completed (when applicable) 
      - If you provided #1 and #2 and it is still unclear on what was done, include a simple explanation or additional visuals to help clarify. 

PLEASE NOTE: IF ANY DESIGN CHANGES ARE MADE OUTSIDE OF THE CAR ISSUES REPORTED, T-SIM CANNOT GUARANTEE THE RESULTS AND A VISUAL CHECK/CONFIRMATION WILL NOT BE SUFFICIENT. 

Refer to the attached PDF below for detailed examples 
    • Related Articles

    • When does T-SIM make changes to Automation, Travel Distances or Design?

      Why would T-SIM service department make changes? We try to avoid making changes, but our goal is to ensure the highest possible SPM, that suppliers are working within the customer standards, and that the automation we are simulating is in fact the ...
    • T-SIM Service Department New Tooling Deliverables and How to Use Them

      T-SIM Service Department Transfer Die Simulation Deliverables for New Tooling Corrective Action Reports: Corrective Action Reports, or CARs as we call them, are the results from the simulation. The CAR's contain all of the issues that need to be ...
    • T-SIM Service Department FAQ

      Who do I work with at T-SIM? Generally, for full list - see T-SIM Contacts What type of Support does T-SIM service department offer? Our service department is available to take meetings to answer questions about Corrective Action Reports and we will ...
    • T-SIM Optimization Levels (Preferences)

      Optimization Level - Plant Optimization Preferences Please note this preference can be for the plant as a whole or specific to individual press lines. T-SIM Service department considers many different sources of information when making decisions on ...
    • Recommended Clearances using T-SIM software

      There are a lot of factors to consider when choosing specific clearances for simulation and optimization. Equipment conditions (transfer slop, gripper air systems, press braking, etc.), controller capabilities, automation, die design, die conditions, ...